Applying for a construction permit for projects and associated structures in Vietnam requires thorough preparation of necessary documents. In 2023, the requirements for permit applications have been updated to ensure legality and efficiency in the construction process. This article provides detailed guidance on the documents needed, helping you navigate the permit application process quickly and in compliance with regulations.
According to Clause 17, Article 3 Construction Law 2014 (revised 2020), construction permit is a legal document issued by a competent state agency to the investor for new construction, repair, renovation, and relocation of works.
- Application for construction permit as prescribed in Form No. 01.
- One of the documents proving land use rights according to the provisions of land law for the project group or the entire project.
- Decision on project approval; Written notice of appraisal results from a specialized construction agency and basic design drawing documents with confirmation stamp attached (if any); Report on the results of construction design verification for construction projects that greatly affect safety and community benefits; Certificate of design approval for fire prevention and fighting and accompanying approved documents and drawings according to the provisions of law on fire prevention and fighting; Written results of implementing environmental protection procedures according to the provisions of law on environmental protection in case of failure to appraise the construction investment feasibility study report at a specialized construction agency;
- 02 sets of construction design drawings in the construction design dossier implemented after the approved basic design according to the provisions of law on construction of each project in the group of projects or the entire project has been approved. approval, including:
+ Construction design documents as prescribed in Point d, Clause 1, Article 43 of Decree 15/2021/ND-CP for non-linear projects;
+ Construction design documents as prescribed in Point d, Clause 2, Article 43 of Decree 15/2021/ND-CP for linear projects.
- Application for license to repair and renovate works and individual houses according to Form No. 01.
- One of the documents proving ownership, management, and use of individual buildings and houses according to the provisions of law.
- Current status drawings of construction parts expected to be repaired or renovated that have been approved according to regulations with a scale corresponding to the scale of the drawings in the application for repair, renovation license and photos. Take photos (minimum size 10 x 15 cm) of the current status of the project and neighboring structures before repair or renovation.
- Repair and renovation design documents corresponding to each type of project as prescribed in Article 43 or Article 46 of Decree 15/2021/ND-CP.
Note: For historical-cultural relics and ranked landscapes, there must be written approval of the necessity of construction and scale of the project from the state management agency. about culture.